Thermal Imaging of a Grade II Listed Property, Liverpool

Graham + Sibbald (G+S) were instructed to provide a defect analysis report and fabric first retrofit to a Grade II listed property in Liverpool. The purpose of the appointment was to;

a) Identify existing building defects and repair as required

b) Produce a specification for repairing and retrofitting the building sensitive to its listing status

c) Invite contractors to tender and complete a tender analysis report

d) Produce architectural drawings and submission of the necessary planning and listed building applications

e) Provide post-contract services as Contract Administrator

f) Provide continual technical support throughout the project

The impact of previous repairs which were not sympathetic to the traditional construction methods have resulted in compounded defects throughout the building leading to moisture becoming trapped within the building fabric. This required significant internal and external works which had to be carefully managed in order to minimise impact to the residents who were to remain in occupation throughout the delivery of the works.

Why G+S

Graham + Sibbald is one of the UK’s leading property consultancy services. Our success is built upon how we deliver our service; it is a unique combination of being both professional and personable.

Our Building Surveying team can help you maximise the value of your property and minimise your costs and liabilities. We work with a broad spectrum of clients, including leading names in the public and private sectors. We represent a wide spectrum of retained clients including Local Authorities, Inward Investors, Government Departments and Major Retailers.

Thanks to our expertise, experience and nationwide network of local offices we are able to deliver a professional, cost-effective service with a real personal touch. We place a high priority on expertise, good communications and building long-term client relationships based on trust.

Approach

The first stage comprised of undertaking an initial site survey to identify the full extent of damage caused by damp and water ingress, ensuring intrusive investigation and remedial treatments were appropriate for an 18th century listed building.

Before works could go out to tender, close communication with local planning and conservation offices was undertaken to ensure the scope of works was sympathetic to the existing structure and character.

The scope of works included replacement of slate roof coverings and lead valleys, replacement + repairs to windows as required, render upgrade works, a full new flat roof waterproofing system, and various internal / external fabric repairs (which included new cast iron rainwater goods + ventilation systems).

Upon award of the contract, we worked closely with the appointed contractor, the Client and service provider to ensure the project was delivered according to their brief and ensured their requirements in time, cost, and quality were satisfied throughout.

Key Challenges

A further challenge was maintaining good communication and professional relationships between the neighbours, service users, management, and families to ensure the works were undertaken safely and at no detriment to the operation of the facility. Additionally, the absence of a temporary roof cover meant the works were highly influenced by the weather conditions, increasing the risk of damage to the internal fabric whilst the building was left exposed.

Results

The project was delivered to the Client's satisfaction despite a number of variations, some in part which were not known until fully exposed, such as the extent of roof or window replacement given access restrictions at the time of the intial survey along with others at the clients request, to ensure the building remained viable as a care facility and building asset in to the 21st century whilst preserving the listed fabric.